What it costs the council to say yes
A section 7.11 developer contribution applies under the Georges River Council Local Infrastructure Contributions Plan 2021, adopted 25 October 2021 and in force from 1 December 2021. Secondary dwellings already get a 50% discount under clause 4.3.6 of that plan, and the figures below are the discounted amounts.
The amount is set by bedroom count, not floor area.
Three things people get caught by:
It is indexed quarterly. The figures above were current for the June 2026 quarter. Confirm the rate that applies on the day you lodge before you budget.
There is no 3-bedroom rate. Council publishes one and 2-bedroom figures and nothing above that. Anyone quoting you a 3-bedroom number for Georges River has worked it out themselves. Ask Council directly if you are going that way.
A section 7.12 levy also exists, and clause 6.1 of the plan says the amount payable is the greater of the 2, not both added together. A $20,000 ceiling applies under clause 4.3.5.
The contribution applies to complying development as well as development applications. Using a private certifier does not avoid it.