What the developer contribution costs, on either pathway
Blacktown charges a section 7.11 developer contribution. Council has confirmed there is no section 7.12 plan, so there is no percentage of cost levy on top.
This one is charged on both pathways. It is payable before work starts on the fast pathway, and before your construction certificate is issued on the council pathway.
The amount is set by bedroom count, not floor area, and 2 definitions catch people out. A bedroom is “a room designed or intended for use as a bedroom or any room capable of being adapted to or used as a separate bedroom”, so a study counts as a bedroom. And “any studio constructed in addition to a secondary dwelling will be deemed to be a separate additional bedroom”, levied a separate one bedroom contribution on top.
Ten separate secondary dwelling rate sheets apply across the local government area, and your lot’s catchment decides which one you get, not your suburb name. We read all 10 on 20 August 2026. They produce the 12 catchment rates below, because a couple of the plans price 2 catchments separately.
Only 3 sheets state a start date, and it is an approval date rather than a payment date: Plan No.1 applies to applications approved from 13 August 2025, Plan No.19 from 20 July 2026 and Plan No.21 from 27 May 2021. The other 7 give no start date at all.
Two further conditions sit on those rates. They assume every other section 7.11 contribution owing on the lot has already been paid. And on Plan No.20 the “within township” traffic component is an estimate only, with the exact fee depending on the developable area assessed at lodgement.
Read this before you budget on those numbers. Every one of the 10 sheets states that its rates apply to payments made by 29 July 2026. We checked Council’s live website on 20 August 2026 and that is still the wording on every sheet, with no replacement published. Council indexes these quarterly, so a new set was due from 30 July 2026 and is overdue. The figures above are the last published rates and are past their own stated validity date. Get a written figure from Blacktown Council before you commit to a budget. Council runs a section 7.11 contributions quote request form and aims to return a written quote in 5 working days, and that written quote is the only number worth building a budget on.
Two plans are also being revised, No.20 (Riverstone and Alex Avenue) and No.22 (to absorb Riverstone East Stage 3), so those rates will move again. Neither covers the 5 suburbs on this page.
Rooty Hill needs its own warning. Rooty Hill appears in 2 different catchments: the No.3 open space catchment shown above, and the No.1 “Plumpton, Rooty Hill and Minchinbury” catchment in Council’s master rate table. Those are very different numbers. Which one applies to your lot is a catchment map question only Council can answer, so do not assume the lower one.