WE BUILD IN SYDNEY, SOUTH COAST (WOLLONGONG) & CENTRAL COAST NSW WE BUILD IN SYDNEY, SOUTH COAST (WOLLONGONG) & CENTRAL COAST NSW WE BUILD IN SYDNEY, SOUTH COAST (WOLLONGONG) & CENTRAL COAST NSW WE BUILD IN SYDNEY, SOUTH COAST (WOLLONGONG) & CENTRAL COAST NSW WE BUILD IN SYDNEY, SOUTH COAST (WOLLONGONG) & CENTRAL COAST NSW WE BUILD IN SYDNEY, SOUTH COAST (WOLLONGONG) & CENTRAL COAST NSW
Skip to main content
Granny Flat News

Granny Flat Build Timeline: What Happens Week by Week

Last reviewed: August 2026

Construction of a granny flat typically runs 12 to 16 weeks from site set-up to handover. The stages happen in a fixed order because each one depends on the last, and knowing that order tells you what you are looking at when you glance out the back window and what you need to have decided by then.

This is a typical sequence. Weather, inspections and site conditions move it around.

The full sequence

Weeks Stage What you will see
1 to 2 Site set-up and excavation Fencing, machinery, earth moving, service trenching
2 to 3 Slab Formwork, steel, plumbing rough-in, concrete pour
4 to 6 Frame and roof The shape of the building appears, then a roof
6 to 8 Lock-up Windows, external doors, external cladding
8 to 9 Rough-in Electrical and plumbing inside the walls
9 to 12 Internal fit-out Insulation, linings, cornices, cabinetry, tiling
12 to 14 Finishes Painting, floor coverings, fixtures, fittings
14 to 16 External works and handover Driveway, paths, landscaping, final inspections

What happens at each stage

Weeks 1 to 2: Site set-up and excavation

Site fencing goes up, access is established, and the ground is prepared. Excavation levels the building area, and service trenches are dug for water, sewer, power and data.

This is the stage where surprises appear. Rock, unexpected soil conditions, or a service in an unexpected position all show up now rather than later.

What you need decided: everything about siting and levels. Changing the position of the building after excavation is expensive.

Weeks 2 to 3: Slab

Formwork is set out, reinforcing steel is placed, and the under-slab plumbing is installed. An inspection happens before the pour, then the concrete goes down and cures.

The slab is a hard commitment point. Plumbing positions are set in concrete, literally.

What you need decided: bathroom, kitchen and laundry layouts, because the drainage positions are fixed here.

Weeks 4 to 6: Frame and roof

The frame goes up and suddenly there is a building. Roof trusses follow, then roofing.

This is the stage where people finally get a feel for the size of the rooms, and where the occasional change of heart happens. Changes here are still possible but they are no longer cheap.

What you need decided: window and door positions, which are framed now.

Weeks 6 to 8: Lock-up

Windows and external doors are installed and the external cladding goes on. Once the building can be locked, materials can be stored inside and weather stops holding things up.

Lock-up is a common progress payment stage.

Weeks 8 to 9: Rough-in

Electrical cabling and plumbing pipework are run through the wall and ceiling cavities before they are closed up. Inspections happen at this point.

What you need decided: every power point, light switch, light fitting and tap position. This is the last easy moment to change them. After the walls are lined, moving a power point means cutting into plasterboard.

Weeks 9 to 12: Internal fit-out

Insulation goes in, then wall and ceiling linings, then cornices and skirtings. Kitchen and bathroom cabinetry is installed and wet area tiling is done.

The building starts to look finished from the inside.

What you need decided: all finishes, because they are being installed. Tiles, cabinetry, benchtops and tapware should have been selected weeks earlier.

Weeks 12 to 14: Finishes

Painting, floor coverings, and the installation of fixtures and fittings. Appliances go in. The building becomes a home rather than a shell.

Weeks 14 to 16: External works and handover

Driveway and paths, any fencing, landscaping and turf. Final plumbing and electrical connections are completed and tested.

Then final inspections, the occupation certificate, and handover.

What happens at handover: you walk through the building with your builder, note any defects, and receive the keys along with your certification and warranty documentation.

The decisions that hold everything up

Looking at the sequence, the same pattern shows up repeatedly. The stages that stall are almost always waiting on a decision rather than on work.

Decision Must be made by
Siting and levels Before excavation
Wet area layouts Before slab
Window and door positions Before frame
Electrical and tap positions Before rough-in
Tiles, cabinetry, benchtops Before fit-out
Paint colours and floor coverings Before finishes

Making all of these before construction starts is the single most effective thing you can do to keep a build on schedule.

What can move the timeline

  • Mostly affects the early stages. Excavation and the slab pour need reasonably dry conditions. Once the roof is on, it matters much less.
  • Several stages require an inspection before the next can start.
  • Rock or unexpected site conditions. Discovered during excavation.
  • Every change you request has a time cost as well as a price.
  • Material or trade availability. Outside anyone’s control, though a builder with steady trades manages it better.

Frequently asked questions

Can I visit the site during construction?

Arrange it with your builder rather than dropping in. Active building sites have safety requirements and there are insurance implications. Most builders are happy to walk you through at agreed times.

Can I make changes during the build?

Yes, but the cost rises sharply the later you leave it. Moving a power point before rough-in is minor. Moving it after the walls are lined and painted is not. Any variation should be documented in writing with a price before the work happens.

What happens if it rains for weeks?

The early stages are affected most, particularly excavation and the slab. Once the building reaches lock-up, internal work continues regardless of weather.

Do I need to be there for inspections?

Generally no. Certifier and trade inspections are arranged by your builder. You will be involved at handover.

What if I find defects at handover?

Note them at the walkthrough. There should be a defects liability period during which they are rectified. Ask your builder how long that period is and how the process works before you sign the contract.

See the process from the inside

Every build follows this sequence, and knowing it makes the whole thing far less opaque.

Read more about our construction process, or call BlueGum on 1300 060 651.

BlueGum Granny Flats is a licensed NSW builder, licence number 247388C. Timeframes in this article are indicative and vary with the site, the weather, inspection scheduling and factors outside any builder’s control.

Free Site Assessment
close slider

Error: Contact form not found.